Project Update

Construction Progress

Follow the journey from foundation to completion

Construction

Building Progress

Enabling Works
Current Phase
8%
Progress
March 2026
Last Updated
Q1 2029
Handover
Overall Progress8%

Timeline

Q3 2024
Dubai Municipality design approval
Preliminary design approval achieved in 19 days — the fastest in the project category.
Completed
Q1 2025
Sales launch & RERA registration
Project registered with RERA (No. 3323). Sales launched with 73 SPAs signed within the first weeks.
Completed
Q4 2025
Enabling works commencement
Site preparation, hoarding installation, and preliminary ground works commenced.
Completed
Q1 2026
Piling & foundation works
Piling works in progress. DEWA substation connection and MEP coordination ongoing.
In progress
Q3 2026
Substructure completion
Foundation and basement levels completion. Superstructure commencement.
Upcoming
2027
Superstructure & core
Vertical construction of the 53-floor tower. Floor-by-floor progress updates will be shared.
Upcoming
2028
MEP, façade & fit-out
Mechanical, electrical, and plumbing installation. Glass façade installation. Interior fit-out commencement.
Upcoming
Q1 2029
Completion & handover
Final inspections, authority approvals, and resident handover.
Upcoming